PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Wire Pulling – Cherry Lane, West Indies Between Northlake Way & N. County Road – Traffic Maintained
Equipment & Conduit Installation – Plantation & Crest Road – Between Northlake Way & The End Of Crest Road. – Road Closed “LOCAL TRAFFIC ONLY” – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – N. Lake Way Between Via Tortuga & Plantation Road (2 Drilling Crews) – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – N. Lake Way Between Via Tortuga & Plantation Road – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – S. Woods Road Between Northlake Way & N. County Road – Lane Closure To Be Implemented – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders on South Ocean Boulevard between Southern Boulevard and Via Del Lago.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous equipment verification and switching orders – Various Locations
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Various gas main relocations.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Cocoanut Row between Royal Palm Way and Australian Avenue.
HDD on South County Road between Royal Palm Way and Seabreeze Avenue.
HDD on Royal Palm Way between Cocoanut Row and South County Road.
HDD services on Seaview Avenue, Brazilian Avenue, and Hibiscus.
Conduit connections, equipment installation, and road restorations on Cocoanut Row between Chilean Avenue & Royal Palm Way, on Australian Avenue between Cocoanut Row and Hibiscus Avenue, and on Brazilian Avenue between Cocoanut Row and Hibiscus Avenue.
Various gas main relocations.
“LOCAL TRAFFIC ONLY”