Traffic Impacts for the Week of 05/13/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL – Wire & Pole Removal Via Crane on List Road & Orange Grove Road – “Road Closed Local Traffic Only”
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling Secondary Service Wire – Miraflores Between Northlake Way & North County Road – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – North Ocean Between Bahama Lane and Eden Road – Lane Closure to Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Alley Between Sandpiper & Eden from Northlake Way To North Ocean – “Road Closed” – No Through Traffic
Equipment & Conduit Installation – North Ocean Between Bahama Lane and Eden Road – Lane Closure To Be Implemented – Traffic Maintained
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
Worth Avenue Conversions to Begin
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Device Installation and Terminations Throughout the Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
Sidewalk restorations and curb installation on Seaspray Avenue, Seaview Avenue, and Royal Palm Way.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations in the Barton Avenue Between Cocoanut Row and South County Road.
HDD on Seabreeze Avenue between South County Road and South Ocean Boulevard.
HDD on South County Road between Seaspray Avenue and Pendleton Avenue.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**