Lane Closure

Traffic Impacts for the Week of 05/29/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and the Phase 5 South Projects

NO WORK ON MONDAY 5/29/2023 IN OBSERVANCE OF MEMORIAL DAY.

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

Transformer Swap Out – Near 1144 North Ocean – Lane Closure To Be Implemented – Traffic Maintained

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

HDD – Private Side Services – Hi Mount Road Between the Intersection of Ridgeview & Hi Mount – “Road Closed Local Traffic Only” Traffic Maintained.

HDD – Private Side Services – West Indies Road (West End) Between North County Road & Northlake Way. – “Road Closed Local Traffic Only” Traffic Maintained.

HDD – Private Side Services – Corner of Plantation Road & Crest Road – “Road Closed Local Traffic Only” Traffic Maintained.

Equipment & Conduit Installation – Hi Mount Road, West Indies & Corner of Plantation Road. –  “Road Closed Local Traffic Only” Traffic Maintained.

Equipment Terminations – Various Locations – No Traffic Impacts

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – N. Lake Way Between Tangier & Miraflores Drive – Lane Closure To Be Implemented – Traffic Maintained

HDD – Tangier Between North County Road & N. Lake Way (West End) – “Road Closed Local Traffic Only” Traffic Maintained

Equipment & Conduit Installation – N. Lake Way Between South Woods Road & Tangier Ave. –  Lane Closure To Be Implemented – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue to wreck out on Algoma Road and South Ocean Boulevard from Southern Boulevard south to project limits. 

Switching orders on Vita Serena to connect PH2S and PH3S.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD services in the 100 & 200 blocks of Brazilian Avenue.

HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on South County Road between Chilean Avenue and Royal Palm Way.

HDD on South Ocean Boulevard between Peruvian Avenue and Brazilian Avenue.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Royal Palm Way in rear easements on the 300 block (lane shifts may be required for equipment staging.)

HDD on Cocoanut Row between Brazilian Avenue and Seaview Avenue.

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Seabreeze Avenue and Royal Palm Way and on Seaspray Avenue between Cocoanut Row and South County Road.

Miscellaneous cable pulling in the 400 blocks of the project limits.