Traffic Impacts for the Week of 06/03/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
FPL – Wire & Pole Removal Orange Grove Road & List Road.- “Road Closed Local Traffic Only”
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Casa Bendita – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Tradewinds Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Alley Between Sandpiper & Eden From Northlake Way To North Ocean – “Road Closed” – No Through Traffic
Equipment & Conduit Installation – North Ocean Between Bahama Lane & Eden Road – Lane Closure To Be Implemented – Traffic Maintained
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
Worth Avenue conversions to continue (No Outages Scheduled)
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Terminations throughout the Phase. Switching Orders as they are released by FPL.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
Sidewalk restorations and curb installation on Seaspray Avenue, Seaview Avenue, and Royal Palm Way.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on South County Road Between Via Bethesda & Royal Poinciana Way.
HDD on Barton Avenue between South Ocean and South County Road.
HDD on Flagler Drive From Barton Avenue To Via Bethesda.
HDD on South County Road Between Seabreeze Avenue and Via Bethesda.
Conduit connections, equipment installation, and road restoration on South County Road, Pendelton from South Lake Trail To South County Road, South Ocean and Chapel Hill Road.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**