Lane Closure

Traffic Impacts for the Week of 06/05/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and the Phase 5 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

Transformer Swap Out – Near 1144 North Ocean – (Dependent on FPL Switching Orders) – Lane Closure To Be Implemented – Traffic Maintained

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Private Side Services – Hi Mount Road Between The Intersection Of Ridgeview & Hi Mount & The Cul-De-Sac – “Road Closed Local Traffic Only” Traffic Maintained.

HDD – Private Side Services – West Indies Road (West End) Near Northlake Way. – “Road Closed Local Traffic Only” Traffic Maintained.

Pulling Wire – Northlake Way Between Ridgeview & Plantation Road – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Corner of Plantation Road & Crest Road –  “Road Closed Local Traffic Only” Traffic Maintained.

Equipment Terminations – Various Locations – No Traffic Impacts

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – N. Lake Way Between Tangier & Miraflores Drive – Lane Closure To Be Implemented – Traffic Maintained 

HDD – Casa Bendita Between North County Road & The Cul-De-Sac – “Road Closed Local Traffic Only” Traffic Maintained.

Equipment & Conduit Installation – N. Lake Way Between Sanford & Tangier Ave. –  Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – La Costa Way Between Northlake Way And The Cul-De-Sac – “Road Closed Local Traffic Only” Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue to wreck out on Woodbridge Road, Clarendon Avenue and South Ocean Boulevard from Southern Boulevard south to project limits. 

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on South County Road between Chilean Avenue and Royal Palm Way.

HDD on South Ocean Boulevard between Peruvian Avenue and Brazilian Avenue.

HDD on Royal Palm Way in rear easements on the 200 block (lane shifts may be required for equipment staging.)

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Royal Palm Way in rear easements on the 300 block (lane shifts may be required for equipment staging.)

HDD on Cocoanut Row between Brazilian Avenue and Seaview Avenue.

Conduit connections, equipment installation, and road restorations on Seaspray Avenue between Cocoanut Row and South Ocean Boulevard and on South County Road between Seabreeze Avenue and Seaview Avenue.

Miscellaneous cable pulling in the 400 blocks of the project limits.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**