Lane Closure

Traffic Impacts for the Week of 06/12/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and the Phase 5 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

Transformer Swap Out – Near 1144 North Ocean – (Dependent on FPL Switching Orders) – Lane Closure To Be Implemented – Traffic Maintained

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

HDD – Private Side Services – West Indies Drive Between Northlake Way & N. County Road. – “Road Closed Local Traffic Only” Traffic Maintained.

Pulling Wire – Northlake Way Between Ridgeview & Plantation Road – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Corner of Plantation Road & Crest Road –  “Road Closed Local Traffic Only” Traffic Maintained.

Equipment & Conduit Installation – East End of Via Linda –  “Road Closed Local Traffic Only” Traffic Maintained.

Equipment Terminations – Various Locations – No Traffic Impacts

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Miraflores Drive Between Northlake Way & N. County Road  –  “Road Closed Local Traffic Only” – Traffic Maintained

HDD – Casa Bendita Between North County Road & The Cul-De-Sac – “Road Closed Local Traffic Only” Traffic Maintained.

Equipment & Conduit Installation – N. Lake Way Between Tangier Ave. & Kawama –  Lane Closure To Be Implemented – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue to wreck out on Clarendon Avenue and South Ocean Boulevard from Southern Boulevard south to project limits. 

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on South County Road between Chilean Avenue and Royal Palm Way.

HDD on South Ocean Boulevard between Peruvian Avenue and Brazilian Avenue.

HDD on Hibiscus Avenue between Chilean Avenue and Royal Palm Way.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on South County Road between Seabreeze Avenue and Royal Palm Way and on Seaspray Avenue between Cocoanut Row and South Ocean Boulevard.

Miscellaneous cable pulling in the 400 blocks of the project limits.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**