Lane Closure

­Traffic Impacts for the Week of 06/17/2024 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 4 NORTH

Clean Up & Complete Removal of Riser Stubs & Any Misc. items Throughout The Phase.

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Service Conversions – Various Locations –  No Traffic Impacts – Traffic Maintained-Awaiting switching orders

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Casa Bendita, Tangier, and Miraflores – No Traffic Impacts – Traffic Maintained

Misc. Wire Pulling – Miraflores, Tangier, and Various Locations – No Traffic Impacts – Traffic Maintained


PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Tradewinds Between Northlake Way & North Ocean – “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Alley Between Sandpiper & Eden From Northlake Way To North Ocean – “Road Closed” – No Through Traffic

Equipment & Conduit Installation – North Ocean Between Bahama Lane & Eden Road – Lane Closure To Be Implemented – Traffic Maintained

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions and remaining switching orders as they are released by FPL.

Worth Avenue Conversions To Continue

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Terminations Throughout The Phase. Switching Orders As They Are Released By FPL.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders as they are released by FPL. Continue conversions as allowable.

Sidewalk restorations and curb installation on Seaspray Avenue, Seaview Avenue, Australian, Chilean, and Peruvian. Misc. Curb Work at Transformer Locations.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Barton Avenue between South Ocean and South County Road.

HDD on Flagler Drive From Barton Avenue To Via Bethesda.

HDD on South County Road Between Seabreeze Avenue And Via Bethesda.

Conduit connections, equipment installation, and road restoration on South County Road From Seabreeze To Breakers Row, Pendleton From South Lake Trail To South Ocean Blvd., and Chapel Hill


“LOCAL TRAFFIC ONLY” 

**All Phases Subject to Change**