Traffic Impacts for the Week of 07/31/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Awaiting FPL Pole Removal Schedule
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
HDD (Service) – El Dorado, W. Indies, & Ridgeview Between Northlake Way & N. County Road – “Road Closed Local Traffic Only” Traffic Maintained.
Pulling Primary Cables – Northlake Way Between El Dorado & Plantation Road – Lane Closure To Be Implemented – Traffic Maintained
Pulling Primary Cables – North County Road Between Country Club Road & Cherry Lane – Working on Shoulder – Traffic Maintained – Flagger Will Be Present
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Tangier Ave. & Miraflores Between Northlake Way & N. County Road – “Road Closed Local Traffic Only” – Traffic Maintained
Equipment & Conduit Installation – Northlake Way Between Tangier & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Tangier & Miraflores Dr. Between Northlake Way & N. County Road – “Road Closed Local Traffic Only” – Traffic Maintained
Pulling Primary Cables – Northlake Way Between Tangier & Sanford – Lane Closure To Be Implemented – Trafic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Pole removal south of Southern Blvd.. Lane Shifts and Flagging During Removal.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous equipment verification and switching orders. Various Locations
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.
HDD on Brazilian Avenue between South Ocean Boulevard and Hibiscus Avenue.
HDD on Hibiscus Avenue between Chilean Avenue and Royal Palm Way.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on South County Road between Seabreeze Avenue and Royal Palm Way, on Cocoanut Row between Royal Palm Way and Seaspray Avenue, and on Seaview Road between South Ocean Boulevard and Four Arts Plaza.
Miscellaneous cable pulling in the 300 & 400 blocks of the project limits.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**