Lane Closure

­Traffic Impacts for the Week of 08/05/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Service Conversions as released by FPL – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Tangier, and Miraflores – No Traffic Impacts – Traffic Maintained
Wire Pulling – Tangier, Miraflores, Chateaux Drive, and North County Road – No Traffic Impacts – Traffic Maintained

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Northlake Way From Tradewinds North To Via Marila Road – Lane Closure To Be Implemented – Traffic Maintained

Wire Pulling – Tradewinds Between Northlake Way & North Ocean Blvd. – No Traffic Impacts

Equipment & Conduit Installation – Sandpiper Between Northlake Way and North Ocean Blvd. –  “Road Closed” Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – Northlake Way From Tradewinds To Sandpiper – Lane Closure To Be Implemented – Traffic Maintained

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions and remaining switching orders as they are released by FPL.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Terminations & Cable Splicing – South Ocean From Brazilian To Peruvian.

Terminations Throughout The Phase. Switching Orders As They Are Released By FPL.

Miscellaneous Sidewalk & Curb Installation Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders as they are released by FPL. Continue conversions as allowable.

Sidewalk & Curb installation on South County Road Between Royal Palm Way & Seaspray.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on South County Road From Breakers Row To Sunrise.

HDD on Royal Poinciana Between Cocoanut And South Country Road.

Conduit connections, equipment installation, and road restoration on South County Road From Breakers Row To Royal Poinciana, Cocoanut Row From Seabreeze To Whitehall, Pendleton From South Lake Trail To South Ocean Blvd., Chapel Hill Road, Primavera, and Antigua Lane.

“LOCAL TRAFFIC ONLY” 

**All Phases Subject to Change**