Lane Closure

Traffic Impacts for the Week of 08/07/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Awaiting FPL Pole Removal Schedule

 PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

HDD (Service) – El Dorado, W. Indies, & Via Linda –  “Road Closed Local Traffic Only” Traffic Maintained.

Pulling Feeder – Northlake Way Between Country Club Road & Plantation –  Lane Closure To Be Implemented – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Tangier Ave. Between Northlake Way & N. County Road  –  “Road Closed Local Traffic Only” – Traffic Maintained

Equipment & Conduit Installation – Northlake Way Between Kawama & Sanford –  Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Tangier & Miraflores Dr. Between Northlake Way & N. County Road –  “Road Closed Local Traffic Only” – Traffic Maintained

Pulling Primary Cables – Northlake Way Between Plantation & Kawama – Lane Closure To Be Implemented – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Pole removal south of Southern Blvd.. Lane Shifts and Flagging During Removal.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders. Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Australian Avenue between South Ocean Boulevard and Hibiscus Avenue.

HDD on Hibiscus Avenue between Chilean Avenue and Royal Palm Way.

Hibiscus Avenue – Closed Between Worth Ave & Peruvian Ave For Median Work / Open To Apollo Parking Lot / Detour In Place

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Royal Palm Way and Seaspray Avenue, on Four Arts Plaza between Royal Palm Way and Seaview Avenue, and on Seaview Avenue between Cocoanut Row and Four Arts Plaza.

Miscellaneous cable pulling in the 300 & 400 blocks of the project limits.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**