Traffic impacts for the week of 08/11/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Finalize Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Concrete Curb – Golfview Road At Corner South Of Everglades Club
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Work At Peruvian Lot For Conversions at 325, & 341 Worth.
Concrete Curb Work In Parking Lot At 354 Chilean
Continue With Wall Mounted Prep Work At 290 S. County Road
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Punch-list Items Generated From Walkthrough. – No traffic impacts
OH Wreck Out – Pole Line Between Seaspray & Seaview (Rear Lot Easement). Crane Set Up Is Dependent On Pole Being Removed.
Concrete Curb Work At 319 & 322 Seaspray
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Execute Switching Orders As They’re Received From FPL – Various Locations – No Traffic Impacts.
Continue With Conversions & Conversion Prep Work
Continue With Concrete Restoration Work Various Locations
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – N. County Road From Wells Road To Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Everglade Ave From Bradley To The Intracoastal – Road Closed – Local Traffic Only – Traffic Maintained.
HDD Drilling (Mainline) -Bradley Place Between Everglade Ave And Dunbar – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End Of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.
Conduit & Equipment Installation – North County Road Between Wells Road And Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On North County From Atlantic Heading South In Southbound Lane- Lane Closure To Be Implemented – Traffic Maintained
HDD On Oleander Between Bradley And County – Road Closed – Local Traffic Only – Traffic Maintained
Tie In Crew On Bradley Place Between Sunrise & Park. Lane Closure To Be Implemented – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep . & Base Rock Installation