Lane Closure

Traffic Impacts for the Week of 08/21/2023 for the Phase 4 North, Phase 5 North,  Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Awaiting FPL Pole Removal Schedule

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Palm Beach Country Club Tunnel Crossing – North Ocean Blvd. – Lane Shift To Be Implemented -Traffic Maintained

Pulling Feeder –  Northlake Way Between RIdgeview & Plantation –  Lane Closure To Be Implemented – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – (Services) – Tangier Ave. Between N. County Road & The Intracoastal  – “Road Closed” Local Traffic Only – Traffic Maintained.

Equipment & Conduit Installation – Tangier Ave. Between N. County Road & Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained.

Equipment & Conduit Installation – Northlake Way Between Kawama & Sanford –  Lane Closure To Be Implemented -Traffic Maintained 

Wire Pulling (Feeder & Primary) – Northlake Way Between Plantation & Sanford – Lane Closure To Be Implemented – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Pole Removal – Various Locations

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders. Various Locations

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Hibiscus Avenue between Worth Avenue and Peruvian Avenue and on Peruvian Avenue between Cocoanut Row and South County Road.

Hibiscus Avenue – Closed Between Worth Ave & Peruvian Ave For Median Work / Open To Apollo Parking Lot / Detour In Place

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Brazilian Avenue and Seaview Avenue, on Four Arts Plaza between Royal Palm Way and Seaview Avenue, and on Royal Palm Way between South Lake Drive and Cocoanut Row.

Miscellaneous cable pulling on Seaspray Avenue, Seaview Avenue, and South Lake Drive.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.

HDD services on Seabreeze Avenue between Cocoanut Row and South County Road.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**