Traffic impacts for the week of 08/25/2025 for Phases 6N, 7N, 3S,4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Finalize Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Concrete Curb – Golfview Rd. at corner south of Everglades Club (Pour early part of next week, will confirm date) – No Traffic Impacts
Concrete Curb – 120 El Brillo Way/640 S. Ocean – curb work at TX (Pour early part of next week, will confirm date) – No Traffic Impacts
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue with wall mounted conduit work at 290 S. County Rd – No Traffic Impacts
Concrete Curb work – 354 Chilean, curb at switch cabinet (Pour early part of next week, will confirm date) – No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead crew – wreck out pole line between Seaspray & Seaview, work between S. County & Ocean with crane set up on Seaspray – Road Closure Pending Crane set up.
Overhead crew – wreck out pole line between Seaspray & Seaview, work west of Coconut, set up on Seaspray west end – Road Closure Pending Crane set up.
Overhead crew – wreck out area surrounding 4 Arts Plaza – Road Closure Pending Crane set up.
Concrete curb work at 319 & 322 Seaspray (Pour early part of next week, will confirm date) – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Prep and execute switching orders as they become available. – No Traffic Impacts
Continue with conversions – No Traffic Impacts
Continue with concrete restoration work – No Traffic Impacts
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – N. County Road From Wells Road To Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Everglade Ave From Bradley To The Intracoastal – Road Closed – Local Traffic Only – Traffic Maintained.
HDD Drilling (Mainline) -Bradley Place Between Everglade Ave And Dunbar – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline & Services) – Canterbury Lane Between North County Road and the East End Of Canterbury. Road Closed – Local Traffic Only – Traffic Maintained.
Conduit & Equipment Installation – North County Road Between Wells Road And Atlantic Ave. – Lane Closure To Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Canterbury Lane & The Cul-De-Sac – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD on N County Rd. working from Everglade south in SB lane. – Traffic Maintained
HDD on Oleander between Bradley PL and N County – Traffic Maintained
HDD on Park Ave between Bradley PL and N County – Traffic Maintained
Tie-In crew working on Bradley PL between Sunset and Everglade. – Traffic Maintained
Tie-In crew working on switches at NE corner of Park and Bradley (150 Bradley PL). – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Subgrade Prep . & Base Rock Installation