Lane Closure

­Traffic Impacts for the Week of 09/02/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and the Phase 6 South Projects

PHASE 5 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Service Conversions – Various Locations –  No Traffic Impacts – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained

Transformer Change Out – 334 Northwoods Road – No Traffic Impacts – Traffic Maintained (FPL Work)

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

HDD – Sandpiper Drive – North Ocean Blvd. To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained

HDD – N. Lake Trail between the “CUT” and Bahama Lane – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Northlake Way From Tradewinds To Via Marila – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Sandpiper Between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained 

Fence Installation – North End Of Palm Beach Country Club – No Traffic Impacts – Traffic Maintained

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions and remaining switching orders as they are released by FPL.

Continue Prep Work On Golfview Alley

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Terminations Throughout The Phase. Switching Orders As They Are Released By FPL.

Miscellaneous Sidewalk & Curb Installation Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Switching orders as they are released by FPL. Continue conversions as allowable.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD – Royal Poinciana and Cocoanut/Bradley Place

Cable Pulling Throughout The Phase – Working South To North – Coordinating With Breakers On S. County.

Conduit connections, equipment installation, and road restoration on Royal Poinciana Way From Cocoanut Row To South County Road. Cocoanut Row From Seabreeze to White Hall. Breakers Golf Course at South County & Main Street, Pendelton from South Lake Trail To South Ocean and miscellaneous locations on Primavera & Antigua Lane.  

Other Traffic Impacts

HOTWIRE WORK UNRELATED TO TOPB UNDERGROUNDING

HDD on Sunset Ave and Bradley Place

Tie-in / Box Installation On Sunset Ave and Bradley Place

***Any Questions Pertaining to this work are to be directed to HOTWIRE or WILCO ELECTRICAL***

“LOCAL TRAFFIC ONLY” 

**All Phases Subject to Change**