Traffic Impacts for the Week of 09/11/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Awaiting FPL Pole Removal Schedule
Punch List Items – Various Locations – Traffic Maintained
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling Feeder & Secondary WIre – Various Locations – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – N. County Road Between Plantation & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Pulling Feeder & Primary – North County Road Between Plantation & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Tangiers Ave. Between Northlake Way & North County Road – “Road Closed” Local Traffic Only – Traffic Maintained.
Equipment & Conduit Installation – North County Road Between Plantation & Sanford – Lane Closure To Be Implemented – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Pole Removal Various Locations. Received No FPL Update
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous loop switching orders. Begin Conversions
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous cable pulling within the project limits.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Royal Palm Way between South Lake Drive and Hibiscus Avenue, on Hibiscus Avenue between Brazilian Avenue and Royal Palm Way, and on South County Road between Royal Palm Way and Seabreeze Avenue.
Miscellaneous cable pulling in the project limits
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.
HDD services on Seabreeze Avenue.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**