PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained
ATT Conduit Repairs – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Bahama Ln – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD – North Alley (South of Garden Road) – Northlake Way to North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Northlake Way From Tradewinds To Bahama – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Sandpiper Between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained
Wire Pulling – Sandpiper Between Northlake Way & North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained
PHASE 2 SOUTH
Replacement of ATT Hand Hole Lids – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions and remaining switching orders as they are released by FPL.
Continue Remaining Prep Work On Golfview Alley
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Terminations Throughout The Phase. Switching Orders As They Are Released By FPL.
Miscellaneous Sidewalk & Curb Installation Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Switching orders as they are released by FPL. Continue conversions as allowable.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD – Royal Poinciana and Cocoanut/Bradley Place
Cable Pulling Throughout The Phase – Working South To North – Coordinating With Breakers On S. County.
Conduit connections, equipment installation, and road restoration on Royal Poinciana Way From Cocoanut Row To South County Road. Cocoanut Row From Seabreeze to White Hall. Breakers Golf Course at South County & Main Street, Pendelton from South Lake Trail To South Ocean and miscellaneous locations on Primavera & Antigua Lane.
MH repair work at Cocoanut & Primavera
“LOCAL TRAFFIC ONLY”