Traffic Impacts for the Week of 09/25/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Minor Punch Out Work – List Road (West End) Between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained.
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Wire Pulling – Feeder- North Ocean Blvd – In Front Of the Palm Beach Country Club & The Beach Club – Lane Closure To Be Implemented – Traffic Maintained
Wire Pulling – Secondary – Various Locations – Lane Closure – Traffic Maintained
Wire Terminations (Feeder) – Various Locations – Lane Closure – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – N. County Road Between Sanford & Miraflores – Lane Closure To Be Implemented – Traffic Maintained
Pulling Feeder & Primary – North County Road Between Tangier & Sanford – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Tangiers Ave. Between Northlake Way & North County Road – “Road Closed” Local Traffic Only – Traffic Maintained.
Equipment & Conduit Installation – North County Road Between Sanford & Miraflores – Lane Closure To Be Implemented – Traffic Maintained
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Pole Removal South of Southern Boulevard, on Via Bellaria, and on Clarendon Avenue.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Switch orders at Everglades Club and Golfview Road. Continue conversions in the southern half of the project limits.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Hibiscus Avenue between Brazilian Avenue and Royal Palm Way.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Royal Palm Way between Cocoanut Row and South County Road, and on South County Road between Royal Palm Way and Seabreeze Avenue.
Miscellaneous cable pulling in the project limits
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.
HDD services on Seabreeze Avenue.
HDD Seabreeze Avenue between intracoastal and South County Road.
“LOCAL TRAFFIC ONLY”
**All Phases Subject to Change**