PHASE 4 NORTH   

Horizontal Directional Drilling / Undergrounding

Minor Punch Out Work – List Road (West End) Between Northlake Way & North Ocean Blvd. –  “Road Closed” Local Traffic Only – Traffic Maintained.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Wire Pulling – Feeder-  North Ocean Blvd – In Front Of the Palm Beach Country Club & The Beach Club –  Lane Closure To Be Implemented – Traffic Maintained

Wire Pulling – Secondary – Various Locations – Lane Closure – Traffic Maintained

Wire Terminations (Feeder) – Various Locations – Lane Closure – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD –  N. County Road Between Sanford & Miraflores  – Lane Closure To Be Implemented – Traffic Maintained

Pulling Feeder & Primary – North County Road Between Tangier & Sanford – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Tangiers Ave. Between Northlake Way & North County Road – “Road Closed” Local Traffic Only – Traffic Maintained.

Equipment & Conduit Installation – North County Road Between Sanford & Miraflores – Lane Closure To Be Implemented – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Pole Removal South of Southern Boulevard, on Via Bellaria, and on Clarendon Avenue.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Switch orders at Everglades Club and Golfview Road. Continue conversions in the southern half of the project limits.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Hibiscus Avenue between Brazilian Avenue and Royal Palm Way.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Royal Palm Way between Cocoanut Row and South County Road, and on South County Road between Royal Palm Way and Seabreeze Avenue.

Miscellaneous cable pulling in the project limits

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Clarke/Barton Alleyways between Cocoanut Row and South Ocean Boulevard.

HDD services on Seabreeze Avenue.

HDD Seabreeze Avenue between intracoastal and South County Road.