Traffic impacts for the week of 09/29/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Finalize Punch List – Various Locations
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions – Various Locations
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead pole removal on Brazilian working east from Hibiscus.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead pole removal on Cocoanut Row working north from Peruvian.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Barton Avenue East of Cocoanut – Lane Closure – Traffic Maintained
HDD on Cocoanut Row Between Clarke Alley and Pendleton Lane – Lane Closure – Traffic Maintained
Prep and execute SO’s as they become available – Various Locations
Continue with conversions. – Various Locations
Continue with concrete restoration work. – North County Road Working South From Royal Poinciana – Lane Closure – Traffic Maintained
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline & Services) – Intersection of Atlantic & Dunbar Between Bradley Place & the Intra-Costal. Road Closed – Local Traffic Only – Traffic Maintained.
HDD Drilling (Mainline & Services) – Bradley Place between Everglade Ave & Wells Road – One lane closure to be implemented – Traffic Maintained.
Conduit & Equipment Installation – Bradley Place between EVERGLADE AVE & Road – Lane Closure to be implemented – Traffic Maintained.
PHASE 8
Horizontal Directional Drilling / Undergrounding
Tie-In Crew Working on Bradley PL between Sunset and Everglade. – Lane Closure – Traffic Maintained
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Pouring Concrete
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**