Lane Closure

­Traffic Impacts for the Week of 1/13/2025 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, Phase 6 South, and Phase 7 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

No work scheduled

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Complete Switching Orders – Various Locations As Released By FPL

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

HDD – Laurian Lane – North Ocean to Northlake Way

Equipment & Conduit Installation – North Ocean Between Garden & Via Marila – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “ROAD CLOSED” 

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Pre-Work with Crane Company For Pole Removal – Schedule Forthcoming

El Bravo Way – Concrete Replacement Pending Concrete Availability

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue With Conversions

Complete Switching Orders – Various Locations As Released By FPL

Complete Make Up & Termination Work Throughout The Phase

Schedule & Coordinate Manhole Work Along South Ocean (3 Locations) – Parking Spots Closure / Lane Shift – Traffic Maintained 

Street Light Controllers / Service Points (2 Locations) 

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

No work scheduled

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Equipment Installation Throughout the Phase – East / West Streets Only – Locations That Do Not Impact North / South Roads

Cable Pulling – Schedule Feeder Cable Pulling on Cocoanut Row – Flagler Museum Working South – SATURDAY 01/11/2025

PHASE 7 SOUTH

Prepare for HDD Residential Services – Sanford Between North County Road & Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**