Traffic Impacts for the Week of 1/13/2025 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, Phase 6 South, and Phase 7 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
No work scheduled
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Complete Switching Orders – Various Locations As Released By FPL
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Laurian Lane – North Ocean to Northlake Way
Equipment & Conduit Installation – North Ocean Between Garden & Via Marila – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “ROAD CLOSED”
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Pre-Work with Crane Company For Pole Removal – Schedule Forthcoming
El Bravo Way – Concrete Replacement Pending Concrete Availability
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Conversions
Complete Switching Orders – Various Locations As Released By FPL
Complete Make Up & Termination Work Throughout The Phase
Schedule & Coordinate Manhole Work Along South Ocean (3 Locations) – Parking Spots Closure / Lane Shift – Traffic Maintained
Street Light Controllers / Service Points (2 Locations)
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
No work scheduled
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Equipment Installation Throughout the Phase – East / West Streets Only – Locations That Do Not Impact North / South Roads
Cable Pulling – Schedule Feeder Cable Pulling on Cocoanut Row – Flagler Museum Working South – SATURDAY 01/11/2025
PHASE 7 SOUTH
Prepare for HDD Residential Services – Sanford Between North County Road & Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**