Traffic Impacts for the week of 10/13/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8, and Clarke Alley
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List Complete – Schedule Walk Through – No Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions As FPL Releases Final Orders – Various Locations
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead Wreckout and Pole Removal Along Brazilian Ave. Working West to East, From Hibiscus Ave. to S. Ocean
Overhead Wreckout and Pole Removal Along Hibiscus Avenue from Royal Palm Way to Peruvian
Overhead Wreckout and Pole Removal Along Chilean from Hibiscus and S. County
Complete Miscellaneous Punch List Items
“Detours To Be Implemented” – Rolling Closures for Pole Removals
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead Wreckout along Cocoanut Row Between Royal Palm Way and Seaspray. (Saturday 10/17/2025)
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Cocoanut Row Between Clarke Alley and Whitehall Way – Lane Closure – Traffic Maintained
HDD on Via Sunny (Will Coordinate with Homeowners)
HDD on Pendleton – Lane Closure – Traffic Maintained
HDD on Barton Ave East of Cocoanut Row – Lane Closure – Traffic Maintained
Prep and execute Switching Orders as they become available – Various Locations
Continue with conversions. – Various Locations
Tie In Crew on S. Lake Trail Between Seabreeze and Antigua Lane.
N. County Road – Execute Switching Orders – Breakers Row to Royal Poinciana – North Bound Lane Closure – Traffic Maintained
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline & Services) – Bradley Place between Dunbar Ave & Wells Road – One lane closure to be implemented – Traffic Maintained.
Conduit & Equipment Installation – Intersection of Bradley Place & Dunbar – Lane Closure to be implemented – Traffic Maintained.
Conduit & Equipment Installation – Intersection of Bradley Place & Wells Road – Lane Closure to be implemented – Traffic Maintained.
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Roadway Reconstruction – Pouring Concrete
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**