Lane Closure

Traffic Impacts for the week of 11/03/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts 

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Residential Conversions As FPL Releases Final Orders – Various Locations 

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreckout and Pole Removal Along Peruvian Ave. Working West To East, From Cocoanut To S. County.

Overhead Wreckout and Pole Removal Along Chilean Between S. County and S. Ocean.

Overhead Wreckout and Pole Removal – Street Light Poles along Australian & Chilean (Friday 11/7/2025)

Overhead Wreckout and Pole Removal – 201 Australian Ave. – Town Parking Lot – North and East Sides – No Traffic Impacts (Saturday 11/08/2025)

Misc. Concrete Work Throughout The Area

Complete Miscellaneous Punch List Items

“Detours To Be Implemented” – Rolling Closures For Pole Removals

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Overhead Wreckout – Misc. Clean Up – Seaspray & Australian – No Traffic Impacts

Work on miscellaneous punch list items – No Traffic Impacts

Misc. Concrete Work Throughout The Area

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Via Bethesda Between S. County Road & Flagler Drive – Lane Closure – Traffic Maintained

HDD on Private Drive Between Antigua Lane & Primavera Ave. – Lane Closure – Traffic Maintained

HDD on Clarke Alley East Of South County – Alley To Close During The Day

HDD on Chapel Hill West Of Cocoanut – Lane Closure – Traffic Maintained

Tie In Crews on Cocoanut, Barton, Flagler, and Pendleton.

Prep and execute SO’s as they become available – Various Locations

Continue with conversions. – Various Locations

Misc. Concrete Work

UPDATE: Monday – Friday, concrete sidewalk removal and restoration on S. County Rd., Western most Southbound lane, rolling closure. 

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling (Mainline) – Dunbar Between Bradley Place & North County Road – Lane Closure To Be Implemented – Traffic Maintained

HDD Drilling (Mainline) – Northlake Way Between Wells Road & Emerald –  Lane Closure To Be Implemented – Traffic Maintained

Conduit & Equipment Installation – Atlantic Between Bradley Place & North County Road – No Traffic Impacts

Conduit & Equipment Installation – Intersection of Bradley Place & Wells Road – Lane Closure to be Implemented – Traffic Maintained.

Conduit & Equipment Installation – Dunbar Between Bradley Place & North County Road – Lane Closure To Be Implemented – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

No Work Scheduled – No Traffic Impacts

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**