Traffic Impacts for the Week of 11/04/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions – Various Locations – No Traffic Impacts – Traffic Maintained . Pending FPL’s Release of Switching Orders
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained. Pending FPL’s Release of Switching Orders
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Via Marila – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD – North Alley (South of Garden Road) – Northlake Way to North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & Adams Street – “Road Closed”
Wire Pulling (Feeder) – Northlake Way & North Ocean Blvd. – “Lane Closure To Be Implemented – Traffic Maintained”
Wire Pulling (Feeder) – Bahama Lane between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained
PHASE 2 SOUTH
No Anticipated Work
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase
Continue Remaining Prep Work On Golfview Alley
Begin Overhead Wreck Out, Prep & Walk Thru, Crane Coordination. Schedule To Be Determined.
Complete Final Conversions and Switching Orders on Island Way and Golfview Alley
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements
Complete Make Up & termination Work Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Misc. Punch List Items Throughout The Phase
Coordinate Phipps Delta Installation – Outage Scheduled for Saturday 11/09/2024 – Pending Approval
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Pulling Throughout The Phase – Working South To North – Coordinating With Breakers With Work On S. County Road.
Conduit connections, equipment installation, and road restoration on Cocoanut Row Between Seaview to Royal Poinciana, Pendleton West of Coconut, Royal Poinciana, South County Road, and Breakers Golf Course
CLARKE ALLEY CLOSURE – CLOSED TO ALL TRAFFIC – Cocoanut Row To County Road – Drainage Work To continue. Approved Traffic Plan To Be Implemented.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**