Lane Closure

­Traffic Impacts for the Week of 11/04/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Conversions – Various Locations –  No Traffic Impacts – Traffic Maintained . Pending FPL’s Release of Switching Orders

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained.  Pending FPL’s Release of Switching Orders

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

HDD – Via Marila – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained

HDD – North Alley (South of Garden Road) – Northlake Way to North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only  – Traffic Maintained

Equipment & Conduit Installation – North Alley Between Northlake Way & Adams Street – “Road Closed”

Wire Pulling (Feeder) – Northlake Way & North Ocean Blvd. –  “Lane Closure To Be Implemented – Traffic Maintained”

Wire Pulling (Feeder) – Bahama Lane between Northlake Way & North Ocean Blvd. –  “Road Closed” Local Traffic Only – Traffic Maintained

PHASE 2 SOUTH

No Anticipated Work

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase

Continue Remaining Prep Work On Golfview Alley

Begin Overhead Wreck Out,  Prep & Walk Thru, Crane Coordination.  Schedule To Be Determined.

Complete Final Conversions and Switching Orders on Island Way and Golfview Alley

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements

Complete Make Up & termination Work Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Misc. Punch List Items Throughout The Phase

Coordinate Phipps Delta Installation – Outage Scheduled for Saturday 11/09/2024 – Pending Approval

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Cable Pulling Throughout The Phase – Working South To North – Coordinating With Breakers With Work On S. County Road.

Conduit connections, equipment installation, and road restoration on Cocoanut Row Between Seaview to Royal Poinciana, Pendleton West of Coconut, Royal Poinciana, South County Road, and Breakers Golf Course 

CLARKE ALLEY CLOSURE – CLOSED TO ALL TRAFFIC – Cocoanut Row To County Road – Drainage Work To continue.  Approved Traffic Plan To Be Implemented. 

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**