Traffic Impacts for the week of 11/10/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8
**NO WORK ON TUESDAY 11-11-2025 IN OBSERVANCE OF VETERANS DAY**
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Residential Conversions As FPL Releases Final Orders – Various Locations
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Overhead Wreckout and Pole Removal – 201 Australian Ave. – Town Parking Lot – North and East Sides – No Traffic Impacts (Saturday 11/08/2025) (REMINDER)
Overhead Wreckout at Chase Bank parking lot, no traffic impacts (Saturday 11/08/2025) (REMINDER)
Overhead Wreckout finish any climbers & clean-up throughout the phase.
Misc. Concrete Work Throughout The Area
Complete Miscellaneous Punch List Items
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
Misc. Concrete Work Throughout The Area
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Barton Alley at Flagler Road – Alley To Close During The Day
HDD on Clarke Alley East Of South County – Alley To Close During The Day
Tie In Crews on South County Road (2 days) Barton, Pendleton, and Chapel Hill. Tie In of ATT Fiber Lines
Prep and execute SO’s as they become available – Various Locations
Continue with conversions. – Various Locations
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – Dunbar Between Bradley Place & North County Road – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline) – Northlake Way Between Wells Road & Emerald – Lane Closure To Be Implemented – Traffic Maintained
Conduit & Equipment Installation – Atlantic Between Bradley Place & North County Road – No Traffic Impacts
Conduit & Equipment Installation – Dunbar Between Bradley Place & North County Road – Lane Closure To Be Implemented – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**