Traffic Impacts for the Week of 11/11/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects
NO WORK ON MONDAY 11/11/2024 IN OBSERVANCE OF VETERAN’S DAY
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Service Conversions – Various Locations – No Traffic Impacts – Traffic Maintained . Pending FPL’s Release of Switching Orders
FPL will be accessing a manhole on Country Club Road, the “S” section of the road between the Beach Club and the Palm Beach Country Club. This manhole work is scheduled for Wednesday 11/13/2024 and Thursday 11/14/2024. A lane closure is necessary and traffic will be maintained.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained. Pending FPL’s Release of Switching Orders
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Via Marila – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD – North Alley (South of Garden Road) – Northlake Way to North Ocean – “Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & Adams Street – “Road Closed”
Wire Pulling (Feeder) – Northlake Way & North Ocean Blvd. – “Lane Closure To Be Implemented – Traffic Maintained”
Wire Pulling (Feeder) – Bahama Lane between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained
PHASE 2 SOUTH
No Anticipated Work
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase
Continue Remaining Prep Work On Golfview Alley
Begin Overhead Wreck Out, Prep & Walk Thru, Crane Coordination. Schedule To Be Determined.
Complete Final Conversions and Switching Orders on Island Way and Golfview Alley Pending Switching Order Release
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Some Switching Orders That Were Released
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements
Complete Make Up & termination Work Throughout The Phase
Plan / Coordinate Outage For 375 South County Road Vault Work
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Misc. Punch List Items Throughout The Phase
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Pulling Throughout The Phase – Coordinating With Breakers With Work On S. County Road.
Equipment Installation Throughout the Phase As Received From FPL
Conduit connections, equipment installation, and road restoration on Cocoanut Row Between Seaview to Royal Poinciana, Pendleton West of Coconut, Royal Poinciana, South County Road, and Breakers Golf Course
CLARKE ALLEY CLOSURE – CLOSED TO ALL TRAFFIC – Cocoanut Row To County Road – Drainage Work To Continue. Approved Traffic Plan To Be Implemented.
COCOANUT ROW CLOSURE – CLOSURE TO BEGIN TUESDAY 11/12/2024 – CLOSED TO ALL TRAFFIC – COCOANUT ROW TO BE CLOSED BETWEEN SEABREEZE AVENUE AND CLARKE AVENUE TO INSTALL A STORM DRAINAGE LINE – APPROVED DETOUR TO BE IMPLEMENTED
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**