Lane Closure

­Traffic Impacts for the Week of 11/25/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

No Traffic Impacts – Awaiting FPL’s Area Work To Be Completed

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained.  Pending FPL’s Release of Switching Orders

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

HDD – Laurian Lane – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained

HDD – North Ocean Between Garden & Via Marila – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only  – Traffic Maintained

Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “Road Closed”

Wire Pulling (Primary) – Via Marilia Between Northlake Way & North Ocean Blvd. –   “Road Closed” Local Traffic Only – Traffic Maintained”

Pouring of Curbs – Various Locations – Traffic Maintained

PHASE 2 SOUTH

No Anticipated Work

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase

Complete Final Conversions and Switching Orders on Island Road If Not Complete This Week .

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements

Complete Make Up & termination Work Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Misc. Punch List Items Throughout The Phase

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Cable Pulling Within Breakers Property 

Equipment Installation Throughout the Phase As Received From FPL

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**