Traffic Impacts for the Week of 11/25/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects
THERE WILL BE NO WORK THURSDAY 11/28/2024 OR FRIDAY 11/29/2024 IN OBSERVANCE OF THANKSGIVING AND TOWN’S HOLIDAY SCHEDULE
**THERE IS TO BE NO LANE CLOSURES ON N/S ROADS – WELLS ROAD TO HAMMON AVE**
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
No Traffic Impacts – Awaiting FPL’s Area Work To Be Completed
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained. Pending FPL’s Release of Switching Orders
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD – Laurian Lane – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained
HDD – North Ocean Between Garden & Via Marila – Lane Closure To Be Implemented – Traffic Maintained
Equipment & Conduit Installation – Via Marila Between Northlake Way and N. Ocean -“Road Closed” Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “Road Closed”
Wire Pulling (Primary) – Via Marilia Between Northlake Way & North Ocean Blvd. – “Road Closed” Local Traffic Only – Traffic Maintained”
Pouring of Curbs – Various Locations – Traffic Maintained
PHASE 2 SOUTH
No Anticipated Work
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Throughout The Phase
Complete Final Conversions and Switching Orders on Island Road If Not Complete This Week .
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Misc. Concrete Work – Bollard Installation – Punch List Items – Mainly Off Peruvian In Rear Lots & Easements
Complete Make Up & termination Work Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Misc. Punch List Items Throughout The Phase
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Cable Pulling Within Breakers Property
Equipment Installation Throughout the Phase As Received From FPL
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**