Traffic Impacts for the week of 12/01/2025 for Phases 6N, 7N, 4S, 5S, 6S, 7S, Phase 8
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (ATT & COMCAST) – North Ocean Between Via Marila & Tradewinds – South Bound Lane -Lane Closure To Be Implemented – Traffic Maintained
FPL Feeder Riser Drop – North Ocean at Boyd’s Park – Lane Closure To Be Implemented – Traffic Maintained
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Misc. Concrete Work Throughout The Area
Complete Miscellaneous Punch List Items
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
Misc. Concrete Work Throughout The Area
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Tie In Crew on Via Bethesda, Barton Ave, Clarke Alley, and Flagler Drive East of S. County Road.
Prep and execute SO’s as they become available – Various Locations
Continue with conversions. – Various Locations
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – Northlake Way Between Wells Road & Emerald – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline) – Atlantic Road At The Intersection Of N. County Road & Atlantic – No Traffic Impacts – Traffic Maintained
Conduit & Equipment Installation – Dunbar Between Bradley Place & North County Road – No Traffic Impacts
Conduit & Equipment Installation – Northlake Way Between Wells Road & Emerald Lane – Lane Closure To Be Implemented – Traffic Maintained
Wire Pulling – Various Locations – No Traffic Impacts
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**