Traffic impacts for the week of 12/15/2025 for Phases 6N, 7N,4S, 5S, 6S, 7S, and Phase 8.
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Replace FPL Feeder Box Lid When Supplied By FPL – No Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (ATT & COMCAST) – North Ocean Between Bahama Lane & The North End Of The Palm Beach Country Club Parking Lot – South Bound Lane -Lane Closure To Be Implemented – Traffic Maintained
Conduit Installation – Alley Between Garden & Eden – “Road Closed” Local Traffic Only
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Miscellaneous Punch List Items No Traffic Impacts
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Work on miscellaneous punch list items – No Traffic Impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Tie In Crew on Clarke Alley, and Flagler Drive East of S. County Road.
Prep and Execute SO’s as they become available – Various Locations
Continue with conversions. – Various Locations
Street Light Controllers & Traffic Signal Breaker Installation – No Traffic Impacts
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling (Mainline) – Northlake Way Between Wells Road & Sanford – Lane Closure To Be Implemented – Traffic Maintained
HDD Drilling (Mainline) – Atlantic Road Between N. County Road & Bradley Place – “ROAD CLOSED” Local Traffic Only – Traffic Maintained
Conduit & Equipment Installation – Northlake Way Between Wells Road & Emerald Lane – Lane Closure To Be Implemented – Traffic Maintained
Wire Pulling – Various Locations – No Traffic Impacts
PHASE 8
Horizontal Directional Drilling / Undergrounding
No Work Scheduled – No Traffic Impacts