Lane Closure

­Traffic Impacts for the Week of 12/16/2024 for the Phase 5 North, Phase 6 North, Phase 7 North, Phase 3 South, Phase 4 South, Phase 5 South, and Phase 6 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

No work scheduled

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Private Side Conversions – Various Locations – No Traffic Impacts – Traffic Maintained. 

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

HDD – Laurian Lane – North Ocean To Northlake Way – “Road Closed” Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – North Ocean Between Garden & Via Marila – Lane Closure To Be Implemented – Traffic Maintained

Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “Road Closed”

Miscellaneous Clean Up For The Holidays Within Phases 5, 6, and 7 North. – No Traffic Impacts

PHASE 2 SOUTH

No Traffic Impacts

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue Misc. Concrete Work – El Bravo Way

Gate & Fence Work on Golfview Alley

INFORMATIONAL ONLY – FPL Area Work – 854 S. County Road – Monday 12/16/2024 and Tuesday 12/17/2024 – Night Time Work – Not Associated With Undergrounding

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Switching Orders – Various Locations As Released By FPL

Continue Misc. Concrete Work – Bollard Installation – Punch List Items – No Traffic Impacts – Back Lot Areas

Complete Make Up & termination Work Throughout The Phase

Street Light Controllers / Service Points (2 Locations) 

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Misc. Punch List Items Throughout The Phase

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Cable Pulling – Only Locations That Do Not Impact North / South Roads – 

Cocoanut Row – Cable Pulling – Once Notifications Are Completed and Night Time Work is Confirmed

Equipment Installation Throughout the Phase – Only Locations That Do Not Impact North / South Roads

Equipment Installation – Pinewalk – NW Corner Of Breakers – Pending FPL Material Delivery

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**