Traffic Impacts for the Week of 12/18/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects
The North projects will work through Wednesday 12/20/2023, then shut down and return on Wednesday 01/03/2024.
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Scheduled To Begin January 2024
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Punch List Items
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue conversions, punch list items, remaining switching orders.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, and road restorations on Australian Avenue between South County Road and South Ocean Blvd.
Miscellaneous cable installation in southern portions of the phase.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Awaiting switching orders. Miscellaneous termination work.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD on Seabreeze Avenue west of Cocoanut Row, Antigua Lane, and Cocoanut Row between Seaspray Avenue and Barton Avenue.
HDD services on Pendleton Avenue and Cocoanut Row.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**