Lane Closure

­Traffic Impacts for the Week of 12/18/2023 for the Phase 5 North, Phase 6 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South and the Phase 6 South Projects

The North projects will work through Wednesday 12/20/2023, then shut down and return on Wednesday 01/03/2024.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Pulling Wire & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Wire Pulling & Terminations – Various Locations – No Traffic Impacts – Traffic Maintained

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Scheduled To Begin January 2024

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Punch List Items

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue conversions, punch list items, remaining switching orders.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Australian Avenue between South County Road and South Ocean Blvd.

Miscellaneous cable installation in southern portions of the phase.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Awaiting switching orders. Miscellaneous termination work.

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Seabreeze Avenue west of Cocoanut Row, Antigua Lane, and Cocoanut Row between Seaspray Avenue and Barton Avenue.

HDD services on Pendleton Avenue and Cocoanut Row.

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**