Traffic Impacts for the Week of 2/10/2025 for the Phase 5, 6, & 7 North, as well as, Phase 2, 3, 4, 5, 6 & 7 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
No work scheduled
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Complete Switching Orders – Various Locations As Released By FPL
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Laurian Lane – Northlake Way To North Ocean – Road Closed – Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “ROAD CLOSED”
PHASE 2 SOUTH
Remove and replace splice box 980 South Ocean / Via Del Lago (Working Through Existing Utility Conflicts)
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Pre-Work with Crane Company For Pole Removal – Schedule Forthcoming
El Bravo Way – Concrete Replacement Pending Concrete Availability
Back Of Esplanade – Concrete Restoration Pending Concrete Availability
Golfview Alley – Complete Work at Open Delta Transformer Now That Phasing Issue Is Resolved
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Conversions
Complete Switching Orders – Various Locations As Released By FPL
**Complete Switching Order at 375 South County** – ALL PARTIES HAVE BEEN NOTIFIED OF APPROVED EARLY START TIME AND SHUT DOWNS
Complete Make Up & Termination Work Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
315 South Lake Drive – Execute Feeder Switching Order In Manhole – A Few Parking Spaces To Be Blocked For Safety – Access to Riser Pole at 440 Royal Palm Also Needed (Pending FPL Release of Order)
Approved Saturday Work (2/15/2025) – FDOT Crosswalk Line Stripping – Royal Palm Way & Cocoanut along with Royal Palm Way & S. County. Weather Permitting.
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Make Up & Termination Work Throughout The Phase
Equipment Installation – Various Locations – No Traffic Impacts
PHASE 7 SOUTH
Prepare for HDD Residential Services – Emerald Lane Between North County Road & Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**