Traffic Impacts for the Week of 2/3/2025 for the North Phases 5N, 6N, 7N, and the South Phases 2S, 3S, 4S, 5S, 6S, 7S
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
No work scheduled
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Complete Switching Orders – Various Locations As Released By FPL
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Laurian Lane – Northlake Way To North Ocean – Road Closed – Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “ROAD CLOSED”
PHASE 2 SOUTH
Remove and replace splice box 980 South Ocean / Via Del Lago
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Pre-Work with Crane Company For Pole Removal – Schedule Forthcoming
El Bravo Way – Concrete Replacement Pending Concrete Availability
350 El Brillo – FPL re-work – Pending FPL final instructions
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Conversions
Complete Switching Orders – Various Locations As Released By FPL
Complete Make Up & Termination Work Throughout The Phase
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
315 South Lake Drive – 02/03/2025 – Pump Down Manhole and Prep For Switching Order
315 South Lake Drive – 02/04/2025 & 02/05/2025 – Execute Feeder Switching Order In Manhole – A Few Parking Spaces To Be Blocked For Safety – Access to Riser Pole at 440 Royal Palm Also Needed
315 South Lake Drive – 02/06/2025 & 02/07/2025 – Execute Feeder Switching Order In Manhole – A Few Parking Spaces To Be Blocked For Safety – Access to Riser Pole at 440 Royal Palm Also Needed (Pending FPL Release of Order)
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Make Up & Termination Work Throughout The Phase
Equipment Installation On Cocoanut Row & Royal Poinciana and at Breakers lot south of Royal Poinciana – No Traffic Impacts
Cable Pulling – Primavera & Barton Alley.
PHASE 7 SOUTH
Prepare for HDD Residential Services – Emerald Lane Between North County Road & Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”