Lane Closure

­Traffic Impacts for the Week of 2/3/2025 for the North Phases 5N, 6N, 7N, and the South Phases 2S, 3S, 4S, 5S, 6S, 7S

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

No work scheduled

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Complete Switching Orders – Various Locations As Released By FPL

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

Equipment & Conduit Installation – Laurian Lane – Northlake Way To North Ocean – Road Closed – Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – North Alley Between Northlake Way & North Ocean – “ROAD CLOSED” 

PHASE 2 SOUTH

Remove and replace splice box 980 South Ocean / Via Del Lago

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Pre-Work with Crane Company For Pole Removal – Schedule Forthcoming

El Bravo Way – Concrete Replacement Pending Concrete Availability

350 El Brillo – FPL re-work – Pending FPL final instructions

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue With Conversions

Complete Switching Orders – Various Locations As Released By FPL

Complete Make Up & Termination Work Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

315 South Lake Drive – 02/03/2025 – Pump Down Manhole and Prep For Switching Order

315 South Lake Drive – 02/04/2025 & 02/05/2025 – Execute Feeder Switching Order In Manhole – A Few Parking Spaces To Be Blocked For Safety – Access to Riser Pole at 440 Royal Palm Also Needed

315 South Lake Drive – 02/06/2025 & 02/07/2025 – Execute Feeder Switching Order In Manhole – A Few Parking Spaces To Be Blocked For Safety – Access to Riser Pole at 440 Royal Palm Also Needed (Pending FPL Release of Order)

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Make Up & Termination Work Throughout The Phase

Equipment Installation On Cocoanut Row & Royal Poinciana and at Breakers lot south of Royal Poinciana – No Traffic Impacts

Cable Pulling – Primavera & Barton Alley.

PHASE 7 SOUTH

Prepare for HDD Residential Services – Emerald Lane Between North County Road & Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained

“LOCAL TRAFFIC ONLY” 