Traffic Impacts for the Week of 3/31/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL & ATT Overhead Line Removal – Various Locations
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Storm Drainage Grouting – Alley Between Sandpiper & Eden. Road Closed – Local Traffic Only – Traffic Maintained – Alley To Be Opened At E.O.B. Daily
Feeder Splicing – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Overhead Wreck Out , Wire & Equipment Removal – East/West Streets – Intracostal To South Ocean – South End Working North – Flagging Operation To Be Implemented
Via Marina & South County Road – Concrete Replacement Pending Concrete Availability
Golfview Alley – Complete Feeder Switching Order Pending FPL Release
Golfview Alley – Fence & Gate Repair/Replacement – Awaiting Fabrication
Asphalt Removal & Bollard Installation – Switch In Ferragamo Parking Lot
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
201 Chilean – Bollard Removal & Conversion Work
Complete Make Up & Termination Work Throughout The Phase / Conversions
Manhole Work – Peruvian Ave. Just West Of South Ocean Near The SW Corner Of 400 South Ocean Including Work In The Manhole At West Side of 400 South Ocean.
Continue With Traffic Signal Power & Controller Installation
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
No Work Anticipated
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Make Up & Termination Work Throughout The Phase
Prep Work For Primary Meter Cabinet Installation – Breakers Golf Course
Complete Primary Cable Installation On Pendleton & Barton
Install Last 3 Single Phase Transformers – Various Locations
PHASE 7 SOUTH
HDD Drilling (Mainline) – Crescent Drive Between North County Road & Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – Wells Road Between Northlake Way and Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – Sanford Avenue Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**