Lane Closure

­Traffic Impacts for the Week of 4/28/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

FPL Overhead Line / Equipment Removal – Various Locations

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Various Locations – No Traffic Impacts

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

Transformer / Primary Terminations – Various Locations – No Traffic Impacts

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue With Overhead Wreck Out , Wire & Equipment Removal – S. County Rd between S. Ocean Blvd and Worth Ave. – Flagging Operation To Be Implemented

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conversions, Switching, and Riser Drops Work Throughout The Phase

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

No Anticipated Work. 

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Miscellaneous Switching Orders As They Are Released By FPL – Various Locations – Traffic to be maintained. 

PHASE 7 SOUTH

HDD Drilling (Mainline) – Wells Road Between Northlake Way and Crescent Drive –  Road Closed – Local Traffic Only – Traffic Maintained

HDD Drilling (Mainline) – North County Road (West Side) – Wells To Sanford – Bike Path Closed – Pedestrian Traffic Maintained

Conduit and Equipment Installation – Emerald Lane Between Northlake Way & Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – Crescent Road Between Emerald and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – West Side of N. County –  Wells To Sanford – Bike Path Closed – Pedestrian Traffic Maintained

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**