Lane Closure

­Traffic Impacts for the Week of 4/7/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects

PHASE 5 NORTH 

Horizontal Directional Drilling / Undergrounding

FPL Overhead Line / Equipment Removal – Various Locations

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List – Various Locations – No Traffic Impacts

FPL Feeder Riser Drop – Northlake Way – Pending FPL Release of Order.

PHASE 7 NORTH


Horizontal Directional Drilling / Undergrounding

Storm Drainage Grouting – Alley Between Sandpiper & Eden. Road Closed – Local Traffic Only – Traffic Maintained – Alley To Be Opened At E.O.B. Daily. Pending Grout Delivery Schedule

Feeder Splicing – Various Locations – No Traffic Impacts

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Continue With Overhead Wreck Out , Wire & Equipment Removal – East/West Streets – Intracostal To South Ocean – South End Working North – Flagging Operation To Be Implemented

Golfview Alley – Complete Feeder Switching Order Pending FPL Release

Golfview Alley – Fence & Gate Repair/Replacement – Awaiting Fabrication

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conversion Work Throughout The Phase

Manhole Work & Switching Order – Vista Switch – 355 South Ocean – Pending FPL Release of Switching Order.

Continue With Traffic Signal Power & Controller Installation

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Seaview Chicane Curb Rework – Pending Concrete Availability

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Continue Make Up & Termination Work Throughout The Phase

Complete Work For Primary Meter Cabinet Installation – Breakers Golf Course

Complete Primary Cable Installation On Pendleton & Cocoanut. Install 3 transformers on Cocoanut. Work to Be Performed On Saturday 3/12/2025.

PHASE 7 SOUTH

HDD Drilling (Mainline) – Crescent Drive Between North County Road & Wells Road  – Road Closed – Local Traffic Only – Traffic Maintained

HDD Drilling (Mainline) – Wells Road Between Northlake Way and Crescent Drive –  Road Closed – Local Traffic Only – Traffic Maintained

HDD Drilling (Mainline) – North County Road (West Side) – Wells To Sanford – Bike Path To Close – Pedestrian Traffic Maintained

Conduit and Equipment Installation – Sanford Avenue Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – Emerald Lane Between Northlake Way & Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained

Conduit and Equipment Installation – Crescent Road Between Emerald and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained

“LOCAL TRAFFIC ONLY” 

**All Phases Subject To Change**