Traffic Impacts for the Week of 4/7/2025 for the Phase 5, 6, & 7 North, as well as Phase 3, 4, 5, 6 & 7 South Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Overhead Line / Equipment Removal – Various Locations
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Various Locations – No Traffic Impacts
FPL Feeder Riser Drop – Northlake Way – Pending FPL Release of Order.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Storm Drainage Grouting – Alley Between Sandpiper & Eden. Road Closed – Local Traffic Only – Traffic Maintained – Alley To Be Opened At E.O.B. Daily. Pending Grout Delivery Schedule
Feeder Splicing – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue With Overhead Wreck Out , Wire & Equipment Removal – East/West Streets – Intracostal To South Ocean – South End Working North – Flagging Operation To Be Implemented
Golfview Alley – Complete Feeder Switching Order Pending FPL Release
Golfview Alley – Fence & Gate Repair/Replacement – Awaiting Fabrication
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Conversion Work Throughout The Phase
Manhole Work & Switching Order – Vista Switch – 355 South Ocean – Pending FPL Release of Switching Order.
Continue With Traffic Signal Power & Controller Installation
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Seaview Chicane Curb Rework – Pending Concrete Availability
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue Make Up & Termination Work Throughout The Phase
Complete Work For Primary Meter Cabinet Installation – Breakers Golf Course
Complete Primary Cable Installation On Pendleton & Cocoanut. Install 3 transformers on Cocoanut. Work to Be Performed On Saturday 3/12/2025.
PHASE 7 SOUTH
HDD Drilling (Mainline) – Crescent Drive Between North County Road & Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – Wells Road Between Northlake Way and Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – North County Road (West Side) – Wells To Sanford – Bike Path To Close – Pedestrian Traffic Maintained
Conduit and Equipment Installation – Sanford Avenue Between Northlake Way & North County Road – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – Emerald Lane Between Northlake Way & Crescent Drive – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – Crescent Road Between Emerald and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
“LOCAL TRAFFIC ONLY”