Traffic Impacts for the Week of 5/12/2025 for the Phase 5, 6, & 7 North, Phase 3, 4, 5, 6, 7 South, and Phase 8 Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Pole Removal – Various Locations
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Pulling in Misc. secondary services – Various Locations – No Traffic Impacts
Wilco ringing out feeder wires – Various locations – No Traffic impact
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
OH team to continue with wire & equipment removal along S. County Rd., currently in the area of El Vedado working South to North. Monday – Thursday, Flagging Operation to be implemented
OH team crew 2, continue with wire, equipment and pole removal on Golfview Alley. – Alley will be closed, BCI to coordinate w/ Town and Residents
Golfview alley fences & gates – Alley will be closed, BCI to coordinate w/ Town and Residents
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue with conversions throughout the phase.
Switching orders as received from FPL, miscellaneous locations.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete punch-list items generated from walkthrough. – No traffic impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete any final termination work, primary meter cabinet terminations. – No traffic impacts
PHASE 7 SOUTH
HDD Drilling (Mainline) – Wells Road Between N. Ocean Blvd and N. County Rd. – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – North County Road (West Side) – Wells To Sanford – East Side of the road – Traffic Maintained
Conduit and Equipment Installation – between the corner of Crescent Road and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
Conduit and Equipment Installation – West Side of N. County – Wells To Sanford – Bike Path Closed – Pedestrian Traffic Maintained
Digging bore pits – Wells Rd. East between N. County Rd and N. Ocean Blvd – “Road Closed” Local traffic Only – Traffic Maintained
Conduit & Equipment installation – Wells Rd. (East) between Crescent Rd. and N. Lake Way – Road Closed – Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
Start HDD on the Northside of Royal Poinciana Way working East to West from N. County Rd.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**