Traffic impacts for the week of 6/20/2022 for the phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and Australian Avenue Watermain projects.
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
Various Location — Equipment Adjustments — No Traffic Impacts
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Cherry Lane, Hi Mount Road, & Ridgeview — Conduit connections & equipment setting. Lane closure. Traffic maintained.
HDD — Country Club Road between North County & Slope Trail. Lane closure. Traffic maintained.
HDD — W. Indies Drive between N. County Road & Northlake Way. Traffic maintained.
HDD — Cherry Lane between Northlake Way & N. County Road. Private side services. Lane closure. Traffic maintained.
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous transformer energizing & conversions Depending on FPL orders being released
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
Conduit connections, equipment installation, road restoration — S. County Road from El Vedado to Island Road. Also on El Brillo Way, El Bravo Way, Gulfstream Road, & Golfview Alley.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — In Rear Easements – Peruvian Avenue Between South County Road & Hibiscus.
HDD — Chilean Avenue Between South County & Hibiscus Avenue.
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Peruvian Avenue Between Cocoanut Row & Southlake Drive
AUSTRALIAN AVENUE WATER MAIN
WATER MAIN INSTALLATION
Australian Avenue — Local Traffic Only- One lane of traffic maintained- NO ON STREET PARKING. Southlake Drive to Cocoanut Row.
Australian Avenue — Local Traffic Only- One lane of traffic maintained- NO ON STREET PARKING. South County Road to South Ocean Blvd.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**