Lane Closure

Traffic impacts for the week of 6/20/2022 for the phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and Australian Avenue Watermain projects.

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Various Location — Equipment Adjustments — No Traffic Impacts

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Cherry Lane, Hi Mount Road, & Ridgeview — Conduit connections & equipment setting. Lane closure. Traffic maintained.

HDD — Country Club Road between North County & Slope Trail. Lane closure. Traffic maintained.

HDD — W. Indies Drive between N. County Road & Northlake Way.  Traffic maintained.

HDD — Cherry Lane between Northlake Way & N. County Road. Private side services. Lane closure. Traffic maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous transformer energizing & conversions Depending on FPL orders being released

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Conduit connections, equipment installation, road restoration — S. County Road from El Vedado to Island Road. Also on El Brillo Way, El Bravo Way, Gulfstream Road, & Golfview Alley.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — In Rear Easements – Peruvian Avenue Between South County Road & Hibiscus.

HDD — Chilean Avenue Between South County & Hibiscus Avenue.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue Between Cocoanut Row & Southlake Drive

AUSTRALIAN AVENUE WATER MAIN

WATER MAIN INSTALLATION

Australian Avenue — Local Traffic Only- One lane of traffic maintained- NO ON STREET PARKING. Southlake Drive to Cocoanut Row. 

Australian Avenue — Local Traffic Only- One lane of traffic maintained- NO ON STREET PARKING. South County Road to South Ocean Blvd.

“LOCAL TRAFFIC ONLY”

**All Phases Subject To Change**