Traffic Impacts for the Week of 6/23/2025 for the Phase 5, 6, & 7 North, Phase 3, 4, 5, 6, 7 South, Phase 8 and Clarke Alley Projects
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Pole Removal – Various Locations
Punch List Items – Various Locations – No Traffic Impacts
PHASE 6 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List – Various Locations – No Traffic Impacts
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Switching Orders As Received From FPL – Various Locations
Residential Conversions – Various Locations – No Traffic Impacts
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
South County Road Closure between Hammon and Worth Ave To Remove Concrete Poles On East Side 6/23/25-6/24/25.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
Continue with conversions throughout the phase.
Complete Switching Order & Splicing two manholes on S. Ocean. One near the east side of 330 Cable Pulling from 330, 350, and 360 S. Ocean Blvd. 6/26/25 – 6/27/25, lane shift to be implemented, traffic maintained.
Coordinate / Schedule 359 S. County Road Meter Bank Replacement
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete punch-list items generated from walkthrough. – No traffic impacts
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Execute switching orders as they’re received from FPL – various location – no traffic impacts.
PHASE 7 SOUTH
HDD Drilling (Mainline) – Canterbury Between N. County Road And The East End Of The Road – Road Closed – Local Traffic Only – Traffic Maintained
HDD Drilling (Mainline) – Coral Lane Between Crescent Road and Northlake Way – Road Closed – Local Traffic Only – Traffic Maintained
Conduit Installation – Coral Lane between N. Lake Way & Crescent Road – “ROAD CLOSED” Local traffic only – Traffic Maintained
Conduit and Equipment Installation – Between the Corner of Crescent Road and Wells Road – Road Closed – Local Traffic Only – Traffic Maintained
Conduit & Equipment installation – Wells Rd. (East) between Crescent Rd. and N. Lake Way – Road Closed – Local Traffic Only – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Bradley Place Between Sunrise Ave. And Seminole.
HDD on Sunset East of Bradley Place – Lane Closure To Be Implemented – Traffic Maintained
HDD on Sunrise East Of Bradley – Lane Closure To Be Implemented – Traffic Maintained
Tie In Crew On Royal Poinciana And Bradley Place
CLARKE ALLEY
CLARKE ALLEY CLOSED FOR ALLEY RECONSTRUCTION – DETOUR IMPLEMENTED
Demolition of Existing Roadway – New Drainage Tops – Subgrade Prep.
“LOCAL TRAFFIC ONLY”
**All Phases Subject To Change**