Lane Closure

Traffic impacts for the week of 08/08/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, Phase 5 South, and Australian Avenue Watermain projects.

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

West End of Orange Grove Road – Splicing Feeder Wire (Feeder Splice Box) –  Lane Closure — Traffic Maintained

**DEPENDENT OF FPL ORDERS**

 PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

HDD — North County Road – From Country Club Road North Through The “S” Bend Up Past the Northern Entrance To The Country Club. – Lane Closure – Traffic Maintained.

HDD — West Indies Drive – Between North County Road & Northlake Way – Lane Closure – Traffic Maintained.

HDD — Services – Country Club Road & West Indies Drive, Polmer Park Road – Lane Closure – Traffic Maintained

Conduit Connections & Equipment Setting – Country Club Road, El Dorado, Windsor Court, & West Indies Drive – Traffic Maintained

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous Transformer Energizing & Conversions Occurring In The Projects Limits Depending on FPL Orders Being Released.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Conduit Connections, Equipment Installation, Road Restoration — S. County Road from Via Marina south to El Vedado Road and on El Brillo Way, El Bravo Way, and Via Marina. Depending on traffic and safety, Via Marina traffic between

South County Road and Middle Road may be detoured via Gulfstream.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Hibiscus Avenue Between Peruvian Avenue & Australian Avenue.

HDD — Chilean Avenue Between South County Road & Hibiscus Avenue.

HDD — Chilean Avenue Between South County Road & South Ocean Blvd.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue Between Cocoanut Row & Southlake Drive

HDD — Private Side Services in the 200/300 Block of Seaspray Avenue.

HDD — Seaview Avenue Between South County Road & Cocoanut Row.

HDD — Seaview Avenue Between South County Road and the intracoastal.

HDD — South County Road Between Seaspray Avenue and Phipps Plaza.

HDD — Cocoanut Row between Royal Palm Way and Seaspray Avenue

AUSTRALIAN AVENUE WATER MAIN

WATER MAIN INSTALLATION

Australian Avenue — Local Traffic Only- One lane of traffic maintained- NO ON STREET PARKING. Cocoanut Row to Hibiscus.

“LOCAL TRAFFIC ONLY”. 

**All Phases Subject To Change**