TRAFFIC IMPACTS WEEK OF 03/14/2022
Below are the traffic impacts for the week of 3/14/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, and Phase 4 South projects.
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
North Ocean Blvd., Northlake Way, & List Road–Pulling Feeder Wire. Lane closure to be implemented. Traffic maintained.
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Hi Mount Road–HDD. Traffic maintained.
Ridgeview Road–HDD from North County to Northlake Way. Lane closure to be implemented. Traffic maintained.
El Dorado Lane–HDD from North County to Northlake Way. Lane closure to be implemented. Traffic maintained.
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous transformer energizing dependent on switching orders from FPL.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Services on Jungle Road & El Vedado
HDD — S. County Road from El Vedado to Island
Conduit Connections, Equipment installation, road restoration — Jungle Road and S. County Road from Banyan Road north to El Vedado Road.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Peruvian Avenue between South County Road and South Ocean Boulevard
“LOCAL TRAFFIC ONLY”.