TRAFFIC IMPACTS WEEK OF 03/21/2022
Below are the traffic impacts for the week of 3/21/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South projects.
PHASE 4 NORTH
Horizontal Directional Drilling / Undergrounding
North Ocean Blvd.–Private side services Colonial to Orange Grove. Lane closure to be implemented. Traffic maintained.
North Ocean Blvd.–Pulling feeder wire between vista and tie pole near List Road. Lane closure to be implemented. Traffic maintained.
PHASE 5 NORTH
Horizontal Directional Drilling / Undergrounding
Hi Mount Road / Ridgeview Drive–HDD. Traffic maintained.
Ridgeview Road–Conduit connections & equipment setting. Lane closure to be implemented. Traffic maintained.
Fairview Road–Conduit connections between N. County Road & Slope Trail. Lane closure to be implemented. Traffic maintained.
PHASE 2 SOUTH
Horizontal Directional Drilling / Undergrounding
Miscellaneous transformer energizing dependent on switching orders from FP&L.
PHASE 3 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Services on Jungle Road, El Vedado, and El Brillo Way.
conduit connections, equipment installation, road restoration — Jungle Road, El Vedado, and S. County Road from Banyan Road north to El Brillo Way.
PHASE 4 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Peruvian Avenue between Hibiscus and South Ocean Boulevard
PHASE 5 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD — Chilean Avenue between South Lake Drive & Cocoanut Row.
“LOCAL TRAFFIC ONLY”