Lane Closure

TRAFFIC IMPACTS WEEK OF 03/21/2022

Below are the traffic impacts for the week of 3/21/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South projects.

PHASE 4 NORTH  

Horizontal Directional Drilling / Undergrounding

North Ocean Blvd.–Private side services Colonial to Orange Grove. Lane closure to be implemented. Traffic maintained.

North Ocean Blvd.–Pulling feeder wire between vista and tie pole near List Road. Lane closure to be implemented. Traffic maintained.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Hi Mount Road / Ridgeview Drive–HDD. Traffic maintained.

Ridgeview Road–Conduit connections & equipment setting. Lane closure to be implemented. Traffic maintained.

Fairview Road–Conduit connections between N. County Road & Slope Trail. Lane closure to be implemented. Traffic maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous transformer energizing dependent on switching orders from FP&L.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

HDD — Services on Jungle Road, El Vedado, and El Brillo Way.

conduit connections, equipment installation, road restoration — Jungle Road, El Vedado, and S. County Road from Banyan Road north to El Brillo Way.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue between Hibiscus and South Ocean Boulevard

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Chilean Avenue between South Lake Drive & Cocoanut Row.

“LOCAL TRAFFIC ONLY”