Lane Closure

Traffic Impacts Week of 04/04/2022

Below are the traffic impacts for the week of 4/4/2022 for the Phase 4 North, Phase 5 North, Phase 2 South, Phase 3 South, Phase 4 South, and Phase 5 South projects.

PHASE 4 NORTH  

Horizontal Directional Drilling / Undergrounding

FPL equipment & wire terminations. No anticipated traffic impacts.

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Hi Mount Road–HDD of services from Ridgeview to north end of road. Traffic maintained.

Ridgeview Road–Conduit connections & equipment setting. Lane closure to be implemented. Traffic maintained.

El Dorado Lane–HDD between N. County Road to Northlake Way. Lane closure to be implemented. Traffic maintained.

Northlake Way–HDD between El Dorado Lane & Country Club Road. Lane closure to be implemented. Traffic maintained.

PHASE 2 SOUTH 

Horizontal Directional Drilling / Undergrounding 

Miscellaneous transformer energizing dependent on switching orders from FPL.

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding 

HDD — Private side services on El Brillo Way.

Conduit connections, equipment installation, road restoration — El Vedado, and S. County Road from Jungle Road north to El Brillo Way.

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Peruvian Avenue in rear lot easements between South County Road and South Ocean Blvd.**There may be equipment parked on Chilean Ave. to perform the work**

HDD — Peruvian Avenue between South County & Hibiscus.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD — Chilean Avenue between South Lake Drive & Cocoanut Row then continuing east towards Hibiscus Ave.

“LOCAL TRAFFIC ONLY”