Lane Closure

Traffic impacts below for the week of 07/13/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List items – Various Locations – No Traffic Impact

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Pendleton Ave (West end at S. County Rd.) – Lane Closure – Local Traffic Only – Traffic Maintained

HDD on S. County Rd. between Pendleton Ave and Pinewalk – Lane Closure – Local Traffic Only – Traffic Maintained. 

Equipment Tie – Ins & Conduit Installation on Pendleton Ave (West end at S. County Rd.) & on S. County Rd from Pendleton Ave to Pinewalk. 

Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.

Overhead Wreck Out – N. County Road between Breakers Row and Royal Poinciana Way – Northbound lane Closure – Traffic Maintained. **PENDING CREW RETURNING FROM STORM DUTY**

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD (Services) – Northlake Way Between Wells Road & Kawama Lane – “ROAD CLOSED” – APPROVED MOVING DETOURS TO BE IMPLEMENTED -Traffic Maintained

Equipment & Conduit Installation – Northlake Way Between Wells Road & Kawama Lane – Lane Closure To Be Implemented – Traffic Maintained

Primary & Secondary Wire Pulling  – Various locations – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

Equipment Tie-Ins & Conduit Installation – Sunset Ave  Between Bradley Pl. and N. County Rd.  – Lane Closure – Local  Traffic Only – Traffic Maintained

Equipment Tie-Ins At Crossing On Root Trail –  Traffic Maintained

COCOANUT ROW WATERMAIN

Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained

**All Phases Subject To Change*