Traffic impacts below for the week of 07/20/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List items – Various Locations – No Traffic Impact

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.

HDD – South County Road Between Pendleton & Pinewalk – Lane Closure To Be Implemented – Traffic Maintained

Tie-In On Pendleton West Of South County & On South County Between Pendleton & Via Bethesda – Lane Closure To Be Implemented – Traffic Maintained

Tie-In & Open Cut Crossings – Via Bethesda & South County Road – Lane Closure To Be Implemented – Traffic Maintained

Overhead Wreck Out – Pole & Wire Removal – South County Road – Breakers To Royal Poinciana – Lane Closure – Traffic Maintained

Overhead Wreck Out – Wire Removal – Royal Poinciana (South Side of East Bound Lanes) –  Lane Closure – Traffic Maintained

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD – Intersection Of Dunbar & N. County Road – Lane Closure With Flaggers -Traffic Maintained

HDD – Intersection Of Wells Road & N. County Road – Lane Closure With Flaggers -Traffic Maintained

Equipment & Conduit Installation – Northlake Way Between Wells Road & Kawama Lane – Lane Closure To Be Implemented – Traffic Maintained

Primary & Secondary Wire Pulling  – Various locations – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

Equipment Tie-Ins & Conduit Installation – Sunset Ave  Between Bradley Pl. and N. County Rd. – Lane Closure – Local  Traffic Only – Traffic Maintained

Equipment Tie-Ins At Crossing On Root Trail –  Traffic Maintained

COCOANUT ROW WATERMAIN

Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained

**All Phases Subject To Change*