Traffic impacts below for the week of 07/20/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
Punch List items – Various Locations – No Traffic Impact
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.
HDD – South County Road Between Pendleton & Pinewalk – Lane Closure To Be Implemented – Traffic Maintained
Tie-In On Pendleton West Of South County & On South County Between Pendleton & Via Bethesda – Lane Closure To Be Implemented – Traffic Maintained
Tie-In & Open Cut Crossings – Via Bethesda & South County Road – Lane Closure To Be Implemented – Traffic Maintained
Overhead Wreck Out – Pole & Wire Removal – South County Road – Breakers To Royal Poinciana – Lane Closure – Traffic Maintained
Overhead Wreck Out – Wire Removal – Royal Poinciana (South Side of East Bound Lanes) – Lane Closure – Traffic Maintained
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD – Intersection Of Dunbar & N. County Road – Lane Closure With Flaggers -Traffic Maintained
HDD – Intersection Of Wells Road & N. County Road – Lane Closure With Flaggers -Traffic Maintained
Equipment & Conduit Installation – Northlake Way Between Wells Road & Kawama Lane – Lane Closure To Be Implemented – Traffic Maintained
Primary & Secondary Wire Pulling – Various locations – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
Equipment Tie-Ins & Conduit Installation – Sunset Ave Between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained
Equipment Tie-Ins At Crossing On Root Trail – Traffic Maintained
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained
**All Phases Subject To Change*