Lane Closure

Traffic impacts below for the week of 07/27/2026 for Phases 7N, 5S, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

Punch List items – Various Locations – No Traffic Impact

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

Concrete Restoration – 417 Peruvian Ave – Parking Spots to be blocked – Traffic Maintained. 

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.

Tie-In On On South County Between Pendleton & Pinewalk – Lane Closure To Be Implemented – Traffic Maintained

Tie-In & Open Cut Crossings – Via Bethesda & South County Road – Lane Closure To Be Implemented – Traffic Maintained

Overhead Wreck Out – Pole & Wire Removal – Cocoanut Row – Seabreeze Ave to Pendleton Ave. – Lane Closure – Traffic Maintained

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

Equipment & Conduit Installation – Relocated Transformer At 158 Dunbar – No Traffic Impacts

Install Service Conduits (Back Yards) – Various Locations – No Traffic Impacts

Primary & Secondary Wire Pulling  – Bradley Place / Northlake Way Between Atlantic Ave & Sanford – Moving Lane Closure – Traffic Maintained

PHASE 8

Horizontal Directional Drilling / Undergrounding

HDD on Sunset Ave between Bradley Pl. and N. County Rd. – Traffic  Maintained

HDD on N. County Rd. between Atlantic and Sunrise – Lane Closure to be implemented – Traffic Maintained.

HDD services on Root Trail between N. County and N. Ocean – Road Closed – Local Traffic Only.

Equipment Tie-Ins & Conduit Installation – Sunset Ave  Between Bradley Pl. and N. County Rd. – Lane Closure – Local  Traffic Only – Traffic Maintained

COCOANUT ROW WATERMAIN

Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained

**All Phases Subject To Change*