Traffic impacts below for the week of 11/30/2026 for Phases 6S, 7N, 7S, 8, and the Cocoanut Row Watermain Projects.

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

OH Wreck Out – (Monday Through Wednesday) – Pole & Wire Removal On North Ocean – ROAD CLOSED LOCAL TRAFFIC ONLY

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Remove / Replace Concrete Near 149 Clarke Ave.

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

Testing of FPL Feeder Cable – Various Locations – No Traffic Impacts

Connections To Transformers & Switches  – Various Locations – No traffic impacts

General Clean-Up In Various Locations Throughout The Project – No Traffic Impacts

PHASE 8

Horizontal Directional Drilling / Undergrounding

HDD mainline conduits in easement  Near 109 Atlantic / 240 N. Ocean– Lane Closures will be implemented – Traffic Maintained

HDD Mainline conduits on Everglade Ave between Bradley Place and N. County Road – Lane Closures will be implemented – Traffic Maintained

HDD Services – Oleander Ave working east to west – Lane Closures will be implemented – Traffic Maintained

Tie In Conduits – Atlantic Ave between N. County Road and N. Ocean – Lane Closures will be implemented – Traffic Maintained

Tie In Conduits On Seminole Between Bradley Place and N. County Road – Lane Closures will be implemented – Traffic Maintained

COCOANUT ROW WATERMAIN

Miscellaneous Punch List Items – No Traffic Impacts