Lane Closure

Traffic Impacts for the Week of 04/10/2023 for the Phase 4 North, Phase 5 North, Phase 6 North, Phase 3 South, Phase 4 South, and Phase 5 South Projects

PHASE 4 NORTH 

Horizontal Directional Drilling / Undergrounding

Private Side Service Connections — Various Locations (Dependent on FPL Switching Orders) – Traffic Maintained

PHASE 5 NORTH  

Horizontal Directional Drilling / Undergrounding

Equipment & Conduit Installation – Plantation Road between Northlake Way & Crest Road – Road Closed Local Traffic Only – Traffic Maintained

Blowing String Lines In Preparation Of Wire Pulling – Various Locations – Traffic Maintained

Wire Pulling (Primary & Secondary) – Northlake Way Between Ridgeview & Plantation-  Lane Closure To Be Implemented – Traffic Maintained

PHASE 6 NORTH

Horizontal Directional Drilling / Undergrounding

HDD –  Northlake Way Between Via Tortuga & Plantation Road – Lane Closure To Be Implemented – Traffic Maintained

HDD – North Woods Road & South Woods Road Between Northlake Way & The Intracoastal – Road Closed Local Traffic Only – Traffic Maintained

Equipment & Conduit Installation – Northlake Way Between Kawama & Via Tortuga – Lane Closure To Be Implemented  – Traffic Maintained. 

Equipment & Conduit Installation – North & South Woods Roads Between Northlake Way & North County Road – Road Closed Local Traffic Only – Traffic Maintained

PHASE 2 SOUTH

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations – FPL Dependent

PHASE 3 SOUTH 

Horizontal Directional Drilling / Undergrounding

Miscellaneous equipment verification and switching orders – Various Locations – FPL Dependent

PHASE 4 SOUTH

Horizontal Directional Drilling / Undergrounding

Conduit connections, equipment installation, and road restorations on Cocoanut Row between Peruvian Avenue and Australian Avenue.

PHASE 5 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD on Cocoanut Row between Royal Palm Way and Australian Avenue.

HDD on South County Road between Royal Palm Way and Seabreeze Avenue.

HDD on Seaview Avenue between South County Road and South Ocean Boulevard.

HDD services on Cocoanut Row between Australian Avenue and Royal Palm Way.

Conduit connections, equipment installation, & road restorations on Cocoanut Row between Chilean Avenue and Brazilian Avenue, on Australian Avenue between South Lake Drive and Cocoanut Row, and on South Lake Drive between Australian Avenue and Royal Palm Way.

“LOCAL TRAFFIC ONLY”

**All Phases Subject to Change**