Traffic impacts below for the week of 06/15/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders / Easement
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.
**Overhead Wreck Out – S. County Road At Seabreese – Working North in the Northbound Lane – Lane Closure To Be Implemented – Traffic Maintained**
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling – (Services) – Northlake Way Between Wells Rd. and Sanford Road. – ” Detours (3 Seperate LocationsThroughout The Week) To Be Implemented” – Traffic Maintained
Equipment & Conduit Installation – Dunbar Road Between Bradley Place & N. County Road – “ROAD CLOSED” – Local Traffic Only – Traffic Maintained
Equipment & Conduit Installation (Backyards) – Atlantic Ave Between Bradley Place and N. County Road – No Traffic Impacts – Traffic Maintained
Primary Wire Pulling – Bradley Place and Northlake Way – Lane Closure To Be Implemented – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD Services On Seminole and Bradley- Lane Closure – Local Traffic Only – Traffic Maintained.
HDD On Sunset Ave. East / West Of Bradley Place – Lane Closure – Local Traffic Only – Traffic Maintained.
HDD On Bradley Place Between Royal Poincianna and Everglade Ave.- Lane Closure – Local Traffic Only – Traffic Maintained
Equipment Tie-Ins & Conduit Installation – Bradley Place, Sunset Ave., Everglades Ave. & Seminole Ave. East of North County Road – Lane Closure – Local Traffic Only – Traffic Maintained
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained
**All Phases Subject To Change**