Lane Closure

Traffic impacts below for the week of 06/22/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.

PHASE 7 NORTH

Horizontal Directional Drilling / Undergrounding

FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders.

Punch List items – various locations – No traffic impact

PHASE 6 SOUTH

Horizontal Directional Drilling / Undergrounding

Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.

Overhead Wreck Out – S. County Rd. between Seabreeze Ave and Royal Poinciana Way: Northbound lanes shifted, 2-Way traffic to be maintained. 

PHASE 7 SOUTH

Horizontal Directional Drilling / Undergrounding

HDD Drilling – (Services) – Northlake Way Between Wells Rd. and Sanford Road. – ” Detours (3 Separate Locations Throughout The Week) To Be Implemented” – Pending Town Approval

Equipment & Conduit Installation – Wells Road East (Back Yards) between N. County Road & N. Ocean Blvd – “ROAD CLOSED” – No traffic impact – Traffic Maintained

Primary & Secondary Wire Pulling  – Various locations – Traffic Maintained

If you have any questions, please let me know.

PHASE 8

Horizontal Directional Drilling / Undergrounding

HDD On Sunset Ave. between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained.

HDD On Sunrise Ave. between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained.

Equipment Tie-Ins & Conduit Installation – Bradley Place between Sunset Ave and Everglade Ave – Lane Closure – Local  Traffic Only – Traffic Maintained

Equipment Tie-Ins & Conduit Installation – Sunset Ave from West of Bradley Pl. to N. County Rd.  – Lane Closure – Local  Traffic Only – Traffic Maintained

COCOANUT ROW WATERMAIN

Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained

**All Phases Subject To Change**