Traffic impacts below for the week of 06/29/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
**THERE WILL BE NO WORK ON FRIDAY JULY 3, 2026 IN OBSERVANCE OF THE 4TH OF JULY HOLIDAY**
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders.
Punch List items – various locations – No traffic impact
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.
Overhead Wreck Out – S. County Rd. between Via Bethesda and Royal Poinciana Way: Northbound lanes shifted, 2-Way traffic to be maintained.
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
Equipment & Conduit Installation – Wells Road East (Back Yards) between N. County Road & N. Ocean Blvd – “ROAD CLOSED” – No Traffic Impact – Traffic Maintained
Primary & Secondary Wire Pulling – Various locations – Traffic Maintained
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Sunset Ave. between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained.
HDD On Root Trail. between N. County Rd. N. Ocean Blvd.. – Road Closed – Local Traffic Only – Traffic Maintained.
HDD On N. County Rd between Sunrise Ave and Atlantic Ave.. – Lane Closure – Local Traffic Only – Traffic Maintained.
Equipment Tie-Ins & Conduit Installation – Bradley Place between Seminole Ave and Atlantic Ave – Lane Closure – Local Traffic Only – Traffic Maintained
Equipment Tie-Ins & Conduit Installation – Sunset Ave from West of Bradley Pl. to N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained