Traffic impacts below for the week of 06/22/2026 for Phases 7N, 6S, 7S, 8, and the Cocoanut Row Watermain.
PHASE 7 NORTH
Horizontal Directional Drilling / Undergrounding
FPL Work Near 911 North Ocean – North Ocean Between Bahama & Jamaica – Waiting on FPL Switching Orders.
Punch List items – various locations – No traffic impact
PHASE 6 SOUTH
Horizontal Directional Drilling / Undergrounding
Complete Remaining Miscellaneous Punch List Items – No Traffic Impacts.
Overhead Wreck Out – S. County Rd. between Seabreeze Ave and Royal Poinciana Way: Northbound lanes shifted, 2-Way traffic to be maintained.
PHASE 7 SOUTH
Horizontal Directional Drilling / Undergrounding
HDD Drilling – (Services) – Northlake Way Between Wells Rd. and Sanford Road. – ” Detours (3 Separate Locations Throughout The Week) To Be Implemented” – Pending Town Approval
Equipment & Conduit Installation – Wells Road East (Back Yards) between N. County Road & N. Ocean Blvd – “ROAD CLOSED” – No traffic impact – Traffic Maintained
Primary & Secondary Wire Pulling – Various locations – Traffic Maintained
If you have any questions, please let me know.
PHASE 8
Horizontal Directional Drilling / Undergrounding
HDD On Sunset Ave. between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained.
HDD On Sunrise Ave. between Bradley Pl. and N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained.
Equipment Tie-Ins & Conduit Installation – Bradley Place between Sunset Ave and Everglade Ave – Lane Closure – Local Traffic Only – Traffic Maintained
Equipment Tie-Ins & Conduit Installation – Sunset Ave from West of Bradley Pl. to N. County Rd. – Lane Closure – Local Traffic Only – Traffic Maintained
COCOANUT ROW WATERMAIN
Installation of New Watermain – Southbound Lane Closure – Cocoanut Row Between Royal Poinciana Way and Pendleton. Lane Closure To Be Implemented – Flagging Operation To Be Implemented -Traffic Maintained
**All Phases Subject To Change**